Powerwall Timelines
Hey everyone, I just went through the process in Houston to get 2x PW3 and expansion pack c/w gateway and manual disconnect. It also ties into my ATS. For those who are wondering, here was my timeline (2025)
$100 Deposit - early June Site Visit - 1 month later, early July Initial quote / plans - +5-10 days System changes - 5 days Fully signed mid July to proceed HOA approval Permits - 5 to 10 days (no permits for me) Interconnection agreement paperwork - late July to mid August (3 weeks ish) Scheduled Install - 5 weeks out 3 weeks in they asked if I was ready in 2 days and I said duhhh 2 days of install with immediate TOU for my free nights plan (only 1 hour without power) Early October PTO, but since I don't have panels doesn't matter.
Really great service / team, awesome installer who worked with me during the process w/ good cable management skills ha.
Still wondering when Tesla Electric is going to show me the fixed and dynamic plans in my app, only time will tell.
Couldn't be happier.
Posted Oct 3, 2025, 5:21 PM UTC