Here’s a look at when Micron hopes to achieve major milestones:

  1. Start clearing trees and building the rail spur.

2025: National Grid starts work on electric, gas lines.

Early 2026: Work begins on childcare site.

Early 2026: County starts work on industrial wastewater plant

Spring 2026: Rail spur is done and construction ramps up.

2028: OCWA starts building new water line from Lake Ontario.

2028: Construction of Fab 1, childcare center complete.

2028: Construction starts on Fab 2

2030: Fab 2 construction done.

2033: Fab 3 construction begins.

2035: Fab 3 complete.

2039: Work begins on Fab 4.

2041: Fab 4 done.

2045: All four fabs running at full capacity