r/enphase•
buttcrackmenace

Proper shutdown & restart procedure?

Had an issue about 2 weeks ago where we had a grid power failure while charging the battery packs. The solar system continues to function overall but something seems to be wrong with the house consumption meter as it no longer reflects the power being used by the house, reading anywhere from 0 to .7kw.

After contacting support it was suggested that an onsite visit may be needed to inspect the CT meter. It was also suggested that the system shut down and restarted. I'd like to do the restart myself rather than paying a technician ~$250 to do it.

It is my understanding that I have to shut items off in a particular order, but all the youtube tutorials I've found don't quite seem to reflect our system setup. Pics follow.

https://preview.redd.it/oldejedveh6h1.jpg?width=4032&format=pjpg&auto=webp&s=f46ff6dbb78394bcadae8a4cef860438da14b1a4

https://preview.redd.it/bhk7pib6fh6h1.jpg?width=3024&format=pjpg&auto=webp&s=1639547323c1b216fe1e14494e802ba8b5b5fcc3

https://preview.redd.it/65rim048fh6h1.jpg?width=3024&format=pjpg&auto=webp&s=33a45486628ed13791438931daa0f9c1a815288f

https://preview.redd.it/0slbm669fh6h1.jpg?width=3024&format=pjpg&auto=webp&s=533576e7cb08fc2b4213dfd03952ed3f00ea15ac

Guidance, please! Which breakers do I flip, and in what order should I flip them?

Posted Jun 10, 2026, 4:35 PM UTC

16