Finally getting some relief on Irvington Rd (Kolb to Houghton)
Phase I: Sierra to Pantano
- Westbound Lane Milling: August 17 -19
- Westbound Lane Bottom Lift Paving: August 26 & 27
- Middle Lane Milling: August 31 - September 2
- Middle Lane Bottom Lift Paving: September 10 & 11
- Eastbound Milling: September 14 - 16
- Eastbound Bottom Lift Paving: September 23 & 24
- Top Lift paving across all lanes: September 28 - October 1
- Striping: October 8
Phase II: Pantano to Kolb
- Westbound Lane Milling: October 5 -8
- Westbound Lane Bottom Lift Paving: October 29 & 30
- Middle Lane Milling: November 2 - 5
- Middle Lane Bottom Lift Paving: November 25 & 25
- Eastbound Lane Milling: November 30 - December 3
- Eastbound Lane Bottom Lift Paving: December 23 & 24
- Top Lift paving across all lanes: January 5 - 8, 2027
- Striping: January 14, 2027