We have all dealt with slow and negligent contractors, but how do you deal with slow and negligent Engineers/Plandesigners?

Im on a job where the Civil design was started 1.5 years ago for a 6.5 acre lot with a simple 55,000 square foot building. Halfway through the original design, the engineer quit and they put some 26 year old kid on it. He redid the plans, failed to look up the metro requirements for utilities, drew some bs plan up that wouldnt pass, then had metro correct him for what was needed. He then sent a 7000 dollar change order in order to redraw the page. 1 week before we can get the grading permit, he notifies us that the state wont give us our NOC because we have two endangered species possibly on our site and that we are to hire a environmentalist to review everything and to answer the states questions. We come to learn that we will not be able to remove any trees after March 31 so we rush to get approvals needed. The last approval we need is from the state. They are requiring the incomplete NOI (that the civil engineer submitted) be completed as well as a bunch of corrections be made to the plans. Many of the errors were simply made because he did not follow their guidelines at all. We need to have this fixed within the next 2 days in order to be able to remove the trees.

If we do not meet this time line, then the entire project is delayed until November. All contracts have been signed, wood has been bought, crews are ready to go. Construction loans is being maturing, etc. All of this, and the Civil engineer is saying that he has an important deadline to meet for another project so he cant work on this one until Thursday or Friday to which it would take a few days to fix the problems.

The civil plans have been submitted 4 times to codes started exactly a year ago. They have been dyed red and rejected all 4 times. They are under review right now with the city and we should get them back approved this week, but i would not be surprised if that did not happen.

I'd say that for each month that this project does not start, about $25,000.00 is lost in hard costs, then another 250,000-400,000 in potential revenue.

What can I do to an Engineer who does not give a fuck, but has me by the balls since it is his stamp on the plans. The boss, of the plan designer, and owner of the company is vacationing 24/7 and is never in contact.

Posted Mar 28, 2017, 4:01 PM UTC

58
my_dog_rescued_me•

At this point I think you should be talking to an attorney. Try submitting this post at r/Legaladvice.

*spelling

10
eckpm•

Get an attorney involved as soon as you can. I'd contact one today.

5
Forester263•

Civil engineer here. Sorry to hear about your troubles - you've been put in a really shitty situation.

Contractually, were you hired by a developer or by the civil engineer in question?

If you and the civil engineer were hired by a developer, under separate contracts, your complaints/damages need to go to the developer, and the developer will deal with the CE.

2
constructorofthingsOP•

We were hired by the developer separately, but I am representing the developer. I am the contractor but also a good friend of the developer. The costs I mentioned where the developers. My costs can be mitigated in creative ways, but my second main concern behind the fact that my friend is getting screwed, is that I assured multiple subs of a very specific time frame for this job to start, this will screw many of them over and I will have to deal with the backlash from that.

1
[deleted]•

[removed]

1
RipcitySun•

You should be compiling all of this info into a folder on your computer because you should be filling a major delay claim. I would write an email to the Engineering Company stating that you are putting them on notice that their lack of design is delaying the project and their company will be held responsible for liquidated damages. (Reread your contract's terminology on dealing with LDs and this might change a bit)

The only thing that you might be in trouble with is that you didn't put them on notice earlier on. Waiting this long on putting people on notice looks kinda negligent in itself.

1
Forester263•

The OP (Contractor) and Engineer are both under separate contracts, through the Developer. The Contractor needs to write the letter to the Developer, and the Developer needs to contact the Engineer.

I don't think the Contractor shouldn't be directly contacting the Engineer to seek damages.

2
RipcitySun•

Right, but you gotta notify both in most cases. Again the OP needs to reread the section in the contract regarding LDs and notifications of delay.

1