Austin, TX Install - Timeline so far...
Thought I'd post here as a data point for others...
- 8/15 - Started the ordering process.
- 8/25 - Design approved (8.92kW panels, 2 PW's)
- 9/14 - Permitting done
Today (9/30) I logged into the portal, as I have done daily, and saw that they scheduled my install date. No notification about it. And the install is scheduled for January 5th, 2022. WTF?
UPDATE: Talked to Tesla - they state that was the date scheduled by my utility, their hands are tied. I called my utility, and they were very nice in letting me know I have no date scheduled, but they were happy to set one up, and told me January 18th, 2022. So I guess I'll be calling back Tesla when I have time to ask them where exactly they got the 1/5/2022 date, and that according to my utility, I don't have a date scheduled.
At least I'm getting a $100 back from my self-referral...
UPDATE 2 - Sad news. I finally got through to Tesla again and explained what Austin Energy told me yesterday - that I had no date scheduled with them, soonest they could give me was 1/18/2022 - and Tesla kept me on the phone while they called to see what was up. They came back and admitted that the 1/5/2022 date shown in my portal was "tentative" and is no longer available, and the soonest they could schedule me for was now........ February 4th, 2022.
I understand the huge delay is on the end of Austin Energy - but Tesla would have fumbled this severely and I believe I would have gotten close to my installation date of 1/5/2022 and they would have told me it was going to be delayed several more months.
I had to say it - but you really do need to act as a Product Manager with Tesla and do the due diligence on what they tell you.
Posted Sep 30, 2021, 5:38 PM UTC · edited
Keeping checking multiple times daily and you will stumble upon closer dates. I did that and moved it up several weeks.
Thanks for the data point - that's encouraging. Definitely will be trying.