vCPU quota limits have me worried
Hey y'all,
My company is launching a new website using Azure. I had no problem spinning up the Dev environment months ago using a total of 12 FsV2 vCPUs among 3 servers. I had to increase the vCPU quota a couple of times to set up these servers along with the domain infrastructure.
I have begun testing to spin up the the staging environment which will be needed soon. Due to always on requirements there will be redundancy which will add around 68 more Fsv2's to our quota requirements among a total of 9 VMs. I tried to increase by 68 and was denied, then had to place a ticket.
They have since increased the quota, but only for what we need right now. They would not add the other 136 vCPUs that will be needed once Production goes live. However, they also won't give me an answer on how much lead time I will need to give them to get those additional cores.
Not sure if this matters, but I have been deploying to East US so far, and half of Prod will go to West US. Another point is that the server requirements are in flux and can change right up until launch. Therefore, we can't feasibly buy reservations this year.
So my questions to you all are:
- Have you ever hit a hard limit on quota increases? Meaning, have you ever been denied when submitting the ticket?
- What is the max lead time you have seen when requesting an increase?
- Is there something I can do differently to avoid this anxiety all together?
Thanks so much for any insight you can give!
Posted May 18, 2022, 3:00 PM UTC
Why would you develop a website to run on VMs?
Admittedly, saying "hosting a website" was extremely reductive.