r/Plumbing•
InfiniZ

Well Pump /w Pressure Tank - Short Cycling

https://i.imgur.com/3sbNeSk.jpg

Above is what I'm working with. I have the tank bled down to just under 28 PSI (from the stock 38). The pump is set to 30/50 (stock) on the pressure switch. Turning it on, everything works beautifully until the tank gauge reads 45 PSI and then the pump short cycles on and off. I'm fairly new to this (if you can't tell by the pvc primer everywhere) and just trying to make use of a cistern we have on the property to water our garden.

Does my system not have the ability to push more than 45 PSI? Should I adjust my pump to 20/40 to compensate?

Let me know if you have any suggestions or if you need any more photos of the system. I've since added in a few unions - one on each side of the pump and one on the outflow side of the tank. Happy to take updated photos if those might be an issue.

Posted Jun 14, 2022, 8:55 PM UTC

19
KJ9983•

Is the air bladder still good inside the tank?

One option you can try is called a cycle stop valve. Here is a link to the manufactures website:

Cycle Stop Valve

1
InfiniZOP•

Tank is new and came in at 38 PSI out of the box. I was able to bleed it down to 28 so I’d assume the bladder is good, otherwise I wouldn’t have any pressure right?

Thanks for the valve suggestion. I’ll take a look.

1
plumbingislife•

Maybe the check valve on the jet pump is bad. You could add a check valve and see if that helps.

1
ParksVSII:Pro: Water Wells & Pumps 🇨🇦•

Remove the check valve between the pump discharge and pressure tank. The pressure switch bounces because the switch can’t “read” the back pressure from the tank. Check valve goes on the suction side of the pump (if there’s a foot valve in the well or cistern it’s not really necessary) or on the discharge side of the tank tee after the main shutoff if you want backflow prevention. If you’re going to do this I suggest a second boiler drain on that side of the check valve to facilitate draining down the system on that side.

1
InfiniZOP•

Ok that was one of my first thoughts. The hookups I had seen before had pressure switches at the tee where the tank was. I was debating on installing one there and just wiring that into the pump instead of the built in one.

The actual cistern hasn’t been in operation for about 10 years so I’m not sure if there is a foot valve, or what kind of shape it’s in. I assume I’d have to dig and follow the in-flow line to find it and where it connects in to the cistern.

I do have another boiler drain on the out-flow line below the shed before it goes into the ground so I should be good there.

I’ll make the switch and report back. Thanks for the info!

1
ParksVSII:Pro: Water Wells & Pumps 🇨🇦•

Yeah, it would work if the switch was on the tank tee; you got it.

Yeah, so in that case you’re safe to stick the CV on the suction side of the pump. It may be a good idea to stick a tee with a threaded port on the other side of it so you can prime the line easily too.

👌👌

1
InfiniZOP•

See my response to the other guy. Got it working and it's running like a dream now. Thanks for the help! Really appreciate it!

2

Yes, check valve needs to be moved to vertical inlet pipe coming from the well. Ok here is how you set a pressure switch. First off I recommend staying low PSI because it looks like your using PVC pipe. Not recommended there but my companies do it copper or pex. So if your tank is set at38 psi. You need to bleed it to 2lbs less then kick in pressing pressure or it will drop out or short cycle. So drain water out after power is off. Lower your tank to about 22 lbs . Once you get a reading off top off tank at that. Then open pressure switch using a blue nut driver, ( only using the taller spring. Back it off about 6 fullrotations. Then manually lift up pressure switch plate so contacts are open. Turn breaker on for about 3-4 seconds. Shut it off . It should build enough pressure to match tanks static pressure. Now go back to nut driver on spring. Tighten it down until contacts are closed. That now is matching tank pressure- give it two full rotations extra as you want your actual kick on pressure to be 2-3 lbs higher to avoid a kick out or pressure loss. Please don’t touch the smaller spring, as it’s already set for a 20 lbs difference. If done correctly it should be tank set to 22 psi. Cut in around 25 psi, cut out at 45 psi. You will have to cycle pump by running faucets to indicate this. Water worker tanks only last best about 5 years I have found. Low quality.

1
InfiniZOP•

Thanks for the info!

Fit in the CV on the vertical intake as it was coming out of the floor, right before the priming tee I have setup there. Switched her on and hummed perfectly and shut off right on queue. Cut-in was about 23 and cut out was 43. Might try upping the pressure if the wife complains - we'll see.

If this was a whole-house system supplying critical water, I probably would have built it with something different. This is just for some automatic watering of our garden and some newly planted trees. The PVC in the ground was already there, I had to remove an old 1/2 hp pump that had seized up because the previous owner didn't drain it come winter, and the old tank that was there had a blown bladder. All of his old PVC was shot too from water freezing in it. If I get 5 years out of this setup, I'll be damn happy.

Thanks for the help everyone!

1