LRT Confederation Line 12 Day Trial Run is Eligible to Start + Detailed Breakdown of Previous and Remaining Work
Below is a list of everything required to achieve RSA/handover of the new Confedration Line LRT. Skip to where it says WE ARE HERE down below if you wanna see what step we are on right now/what’s left. TLDR at the bottom.
.
1: Belfast yard and the connector tunnel to the main line must be completed.
2: The 12.5 km of track and the downtown tunnel must be completed.
3: The caternary system of overhead wires and poles for electrical distribution to the trains must be completed.
4: All stations must be completed and have received their occupancy permits.
5: All trains must be built and tested, receiving their safety certification from Thales.
Note: There’s a million other things that must be completed here, but I can’t list them all. Basically, all the construction AND testing should be done at this point, excluding the 12 day trial run.
.
.
6: RTG claims they have achieved substantial completion
-This means everything major is done. The only things that can be left at this point are minor deficiencies that would not delay the opening of the line/the line could open even with whatever minor issue is left. Things like paint needs to be added to a random spot at Blair.
-RTG submits their substantial completion paperwork to the city
.
7: The city reviews RTG’s claim of having achieved substantial completion
-The city will agree or disagree
-The city has 5 days to make a decision
-Regardless of the city’s decision, both RTG’s claim and the city’s agreement/disagreement will be sent to an independent certifier
-Note: The city of Ottawa did not agree with RTG’s claim of having reached substantial completion
.
8: Independent Certifier judges whether RTG has achieved substantial completion or not.
-Certifier has 5 days to make a decision
-WE ARE HERE. If they side with the city, the certifier explains what the outstanding issues are and we return to step 6. (Certifier sided with the city, now RTG has to fix the issues and submit a new claim of substantial completion. Once they do that, we're back at step 6.)
-If they side with RTG, then RTG has achieved substantial completion and is eligible to continue to the 12 day trial run
.
9: 12 Day Trial Run Begins
-RTG must run the system as if it was in full weekday and weekend service for 12 days with no major issues
-Minor issues are acceptable and won’t restart the clock
-Major issues will restart the clock back to day 1
.
10: Safety Auditor does a final check and certifies the system as safe and complete.
-With this step, RSA has been achieved and handover of the system to the city of Ottawa occurs.
.
11: City of Ottawa requires 2-4 weeks of additional work/testing/training before opening the line to paying customers.
.
Assume it will take 4 weeks. .
TLDR: RTG claimed they have achieved substantial completion, the city disagreed. An independent certifier agreed with the city. RTG has to fix the issues, and submit a new claim of substantial completion, returning us to step 6.
edit: Formatting, spelling, typos.
Edit: New info shows previous info was inaccurate. The certifier actually sided with the city, post has been amended to reflect that.
Posted May 14, 2019, 2:05 AM UTC · edited
I would have to admit.... if it is up and running by Bluesfest that would be pretty nice. Will also be a shit show though.
[deleted]
Unlike bluesfest of the past, there weren't buses every 3-5minutes
Let’s hope Bluesfesters are less likely to piss in moving train cars than they are on people’s front lawns.
Someone has to christen the new trains :)
Will the trial run include urine? 😁
The LRT is designed to move 10,700 people per direction per hour so both Canada Day and Blues Fest would be a great way to test that claim! :)
Rush hour would sufficiently demonstrate that capability. ~11,000 ppdph is how many people travel by public transit through the core at rush hour!
Right yes but I meant more to how the human traffic flow would be for BluesFest or Canada Day when a shit-ton of people all gun for the train after the concerts (or fireworks) are over from one main station where as during rush hour, the loading is kind of split across several stations.